COMPANY PROFILE / HYDROGEN ENERGY

Asahi Kasei
Taking five decades of chlor-alkali cell expertise into alkaline water electrolysis, a hydrogen business that entered its commercialization phase in fiscal 2025

Asahi Kasei is part of the hydrogen story because it is a company that has supplied membranes, electrolyzers, electrodes, operating know-how and monitoring for ion-exchange-membrane chlor-alkali electrolysis, and is now applying the same electrochemical principle to splitting water. At the Fukushima Hydrogen Energy Research Field (FH2R) it has run a 10 MW-class alkaline water electrolyzer since March 2020, and at its Kawasaki Works a pilot plant of four 0.8 MW modules is used to test how several modules are controlled together. In July 2025 it won an order for a 1 MW-class containerized unit from Finland, which the company describes as its first order since commercialization. This profile covers the hydrogen business only, not Asahi Kasei as a whole, and sets out from primary sources what the company has committed, with whom it works and how much it discloses.

Sources: Asahi Kasei's 135th Securities Report (April 2025 to March 2026), its financial results for the year to March 2026, the Aqualyzer website and brochure, official press releases and NEDO public documents, used as primary material. Last updated October 2026.

What this article covers
  1. Asahi Kasei in 30 seconds, and where it stands in hydrogen energy
  2. The logo and how the name is written
  3. Where the company sits in the field
  4. Scale
  5. Resources committed to hydrogen energy
  6. What it has done so far
  7. What comes next
  8. What the company is aiming for in hydrogen energy
  9. Map of partnerships in hydrogen energy
  10. Technologies, products and services
  11. The risks this company carries
  12. Glossary, references and claim-to-source audit

1. Asahi Kasei in 30 seconds, and where it stands in hydrogen energy

LEGAL NAMEAsahi Kasei CorporationFounded in 1922
HEADQUARTERSTokyo, JapanHibiya Mitsui Tower, Yurakucho, Chiyoda-ku
LISTINGTokyo Stock Exchange
securities code 3407
As stated in the results for the year to March 2026
CATEGORY IN THIS FIELDElectrolyzers (primary)
Materials & components (secondary)
Alkaline method; also makes cell frames and membranes for chlor-alkali
HOW THE COMPANY RANKS ITA "strategic cultivation" businessMedium-term plan 2027 (the English releases say "Growth Potential"); part of Energy & Infrastructure
PRODUCT NAMESAqualyzer
Aqualyzer-C³
Large systems, and a 1 MW-class containerized unit
OPERATING RECORD10 MW-class since March 2020
(FH2R)
Plus a 0.8 MW x 4-module pilot plant in Kawasaki
ORDERSJuly 2025
Finland (1 MW-class)
The company calls it its first order since commercialization
The one thing to grasp first

Asahi Kasei's hydrogen business is neither "a company that sells hydrogen" nor "a company that only sells electrolyzers". It is a company that has handled membranes, cells, electrodes, operation and monitoring for chlor-alkali plants, and is extending the same kind of electrolysis equipment to water electrolysis Sourced. The new Kawasaki plant approved in October 2025 is planned to make cell frames and membranes for both water electrolysis and chlor-alkali on the same lines, and the company says it will run chlor-alkali and water electrolysis as twin pillars Sourced. Sales, profit and headcount for the hydrogen business alone are not disclosed, and the only order we could confirm from primary sources is one 1 MW-class unit Not yet confirmed. The 100 MW-plus business the company talks about is still ahead of it.

2. The logo and how the name is written

A note on names: the legal entity is Asahi Kasei Corporation (Asahi Kasei Kabushiki Kaisha in Japanese). This profile covers the hydrogen business only, and is written afresh from a hydrogen perspective, separately from the Asahi Kasei profile in this series' polymers and resins field. Aqualyzer and Aqualyzer-C³ are Asahi Kasei product names, not legal entities. Cefmof (Central Finland Mobility Foundation) in Finland is the customer, not an Asahi Kasei subsidiary. The logo is the white version published on Asahi Kasei's official Aqualyzer website, shown on a dark background.

Official site: https://www.asahi-kasei.com/

3. Where the company sits in the field

Four types of company in hydrogen energy All are hydrogen companies, yet strengths and customers differ widely Electrolyzers Fuel cells, end-use Gases, large projects Materials, components Makes hydrogen from water Converts hydrogen to power Makes and moves hydrogen Membranes and catalysts nucera / ITM Power Plug Power / Nel Ballard / Bloom Energy Toyota / Kawasaki Heavy Air Products / Linde Air Liquide / ACWA Chemours / AGC Johnson Matthey, others Track record and capacity Proven products per use Gas networks and capital Quality and consistency Project and policy driven Use-case ramp-up risk Payback on big capex End-demand dependent Mainly the left-hand box (alkaline electrolyzers), secondarily materials and components Applies chlor-alkali cell and membrane know-how to water electrolysis; hydrogen sales not disclosed
Fig. 1 Four types of company in hydrogen energy, and where Asahi Kasei sits. The classification is ours, based on the company's own description (water electrolysis systems, and supply of cell frames and membranes) Our calculation. “Fuel cells & end-use” stands for Fuel cells & hydrogen end-use equipment. Companies named are examples from this series.

4. Scale

Asahi Kasei is a diversified chemicals group with three sectors: Healthcare, Homes and Material. The hydrogen business belongs to the Energy & Infrastructure business inside Material, and its sales and profit are not reported separately. Only the company-wide figures and those of the segment it belongs to are shown here Sourced.

Indicator (¥ million)Year to March 2025Year to March 2026
Net sales (consolidated)3,037,3123,074,505
Operating profit (consolidated)211,921231,200
R&D expenses (whole group)110,641110,537
Material segment net salesn/aabout ¥1,306.2 billion (operating profit about ¥68.3 billion)
Capital expenditure (tangible and intangible, excluding goodwill, acceptance basis)n/a222,324

Consolidated employees number 47,895 (as of 31 March 2026) and paid-in capital is ¥103,389 million. In the Securities Report, the Material segment accounted for the largest capital expenditure in the year to March 2026 (¥164.8 billion), but the main items listed are higher coating capacity for lithium-ion battery separators and the refurbishment of hydroelectric plants; water electrolysis facilities are not listed.

A caution

The figures above are for the whole company or the whole Material segment and do not show the size of the hydrogen business. The Securities Report does not break out sales, profit, R&D spending or headcount for hydrogen. This article does not estimate them Not yet confirmed. A 2021 business strategy vision submitted to NEDO contains a sales plan for water electrolysis (¥29.0 billion in fiscal 2030 and ¥58.8 billion in fiscal 2035), but that is a plan made when the project began, not a result.

5. Resources committed to hydrogen energy

Most figures for money and people are not disclosed for hydrogen alone. What could and could not be confirmed is set out below.

ResourceWhat primary sources confirmCategory
PeopleThe hydrogen work is attributed to the Green Solution Project (by the company's account, mainly element technologies such as efficiency and degradation control in alkaline electrolysis) and to Corporate Production Technology (system development such as scale-up and response to fluctuating input). Six engineers from these two units (three each) received a technical award from the Electrochemical Society of Japan in March 2026. The headcount for hydrogen is not disclosedSourced / not disclosed
Money (R&D)Group R&D spending was ¥110.5 billion (year to March 2026). The hydrogen share is not disclosedSourced / not disclosed
Money (capital expenditure)New Kawasaki plant for cell frames and membranes: the December 2024 announcement put total investment at about ¥35 billion (with a subsidy of up to ¥11.4 billion expected); the October 2025 decision gives about ¥31 billion (of which up to one third is a subsidy under the GX Supply Chain Development program). The company states it is still refining the design and that the figure may changeSourced (plan)
Investments and partnershipsDecision to take a stake in Ionomr Innovations of Canada (anion exchange membranes for water electrolysis), December 2023. MOU with De Nora of Italy on developing and selling containerized systems (September 2024). Joint proposal with JGC Holdings to the Green Innovation Fund. MOU with Gentari on a Malaysian project (November 2023). Acquisitions, joint ventures or divestments in hydrogen: none confirmedSourced / none confirmed
Public funding and research bodiesNEDO commissioned project (FH2R, from 2020); NEDO Green Innovation Fund (a subsidy for building and running the Kawasaki pilot plant); METI's GX Supply Chain Development program (selected December 2024). No named university collaborations could be confirmedSourced / none confirmed
Industry bodiesJoined the Hydrogen Council as a steering member (October 2022) and the Japan Hydrogen Forum in the U.S. (July 2023)Sourced

Status of main projects

ProjectLocationScaleStageDates and notes
FH2R (Fukushima Hydrogen Energy Research Field)Namie, Fukushima, Japan10 MW-class (about 200 cells)Operating demonstrationStarted March 2020; the company said in May 2024 it had run it for over four years. NEDO commissioned project
Kawasaki pilot plantKawasaki Works, Kanagawa, Japan0.8 MW x 4 modulesDemonstration under wayConstruction announced November 2022; trial run completed March 2024; opening ceremony 13 May 2024. Supported by the NEDO Green Innovation Fund
Cefmof hydrogen stationJyväskylä, Finland1 MW-class; about 400 kg/day at full outputInstallation under way (Not yet confirmed)Ordered July 2025; installation began March 2026. Hydrogen production is planned from around July 2026, with steady operation within the year. We could not confirm that production has started
Green ammonia demonstration (JGC Holdings)Namie, Fukushima, JapanUses hydrogen from the FH2R electrolyzerDescribed by the company as under construction (November 2023)NEDO noted in July 2025 that delivery of some equipment was delayed
60 MW-class project (Gentari, JGC Holdings)Malaysia60 MW-class; 8,000 tonnes/year of green hydrogenMOU to move to front-end engineering design (FEED), November 2023The company aimed for demonstration operation in 2027. NEDO noted in July 2025 that the Green Innovation Fund's "Phase 2" had its overseas demonstration site under review (it does not name Malaysia, but Asahi Kasei treats this project as Phase 2). We could not confirm what has happened since
European demonstrations (ALIGN-CCUS, TAKE-OFF)GermanyMid-sized electrolyzerDemonstration (from 2020)The company says the hydrogen is used with CO₂ from a power plant to synthesize sustainable aviation fuel (SAF)
A materials engineer's view: fifty years of consumable-part experience is now a target value

The 2021 business strategy vision submitted to NEDO sets, as a target for water electrolysis element technology, "consumable-part life of four years or more (fiscal 2023)", and gives as its basis the service life of consumables in chlor-alkali electrolyzers Sourced (a plan from the start of the project, not a report of achievement). An electrolyzer keeps its performance by replacing consumable parts such as diaphragms, electrodes and gaskets. A company that has long managed membrane and electrode life in chlor-alkali plants is carrying that yardstick over to water electrolysis. There is a difference, however: chlor-alkali plants run on steady power, whereas electrolyzers fed by renewable energy see fluctuating output and more stops and starts. Whether the same life target can be met under fluctuating input is what the multi-module tests in Kawasaki are checking Not yet confirmed.

6. What it has done so far

WhenWhat happenedWhy it matters
1923Began producing hydrogen by water electrolysis with hydroelectric power in Nobeoka, Miyazaki, as a feedstock for ammoniaOrigin of the company's electrolysis business (per the brochure)
1975Commercialized ion-exchange-membrane chlor-alkali electrolysis systemsThe technical foundation for water electrolysis. Cumulative scale is the company's own description (below)
2010Began developing alkaline water electrolysis systemsThe company says it has kept testing with scale-up and mass production in mind since then
2020Joined the European project ALIGN-CCUS (moving to its successor TAKE-OFF from 2021). In March, started the 10 MW-class unit at FH2RA mid-sized European demonstration alongside a large domestic one
October-November 2022Joined the Hydrogen Council (28 October). Announced construction of the Kawasaki pilot plant (7 November)International network, and the start of multi-module testing
July-December 2023Joined the Japan Hydrogen Forum. In November, MOU with Gentari and JGC Holdings on a 60 MW-class project. In December, decided to take a stake in Ionomr (AEM membranes)Links to the U.S. and Southeast Asia, and an investment in next-generation membranes
March-May 2024Completed a trial run with hydrogen production at the Kawasaki pilot plant (March). Opening ceremony on 13 MayMulti-module control tests begin in earnest
September 2024MOU with De Nora on developing and selling containerized systemsA compact, distributed line alongside the large Aqualyzer
December 2024Selected for METI's GX Supply Chain Development programTowards mass-production facilities for cell frames and membranes
July 2025Cefmof ordered a 1 MW-class Aqualyzer-C³The company calls it its first order since commercialization and says its hydrogen business has moved fully into the commercialization phase
October 2025Formally decided to build the new Kawasaki plant (cell frames and membranes, over 2 GW each; start-up planned in fiscal 2028)Investment announced as about ¥31 billion (may change)
March 2026Installation began in Finland (12 March). Won the Electrochemical Society of Japan's 2026 Technology Award, the Tanahashi Prize (ceremony 18 March, announced 19 March)Awarded for the development and long-term demonstration of a 10 MW-class large alkaline water electrolyzer

7. What comes next

NEW PLANT (CELL FRAMES AND MEMBRANES)Start-up planned in fiscal 2028Over 2 GW each; with existing chlor-alkali lines, over 3 GW a year
1 MW-CLASS UNIT IN FINLANDHydrogen production from around July 2026Steady operation within the year. Company plan
SCALING UPCommercializing 100 MW-plusDesign to combine FH2R and Kawasaki data
MARKET SHARE TARGET20% around 2030In the major markets, mainly Europe, North America and Asia. Company target

All of these are company plans and targets, not things that have happened Not yet confirmed. The timing has shifted a little with each announcement.

When announcedWhat the company said (how timing and numbers have changed)
October 2022To bring to market by 2025 a large unit made of several 10 MW modules, based on FH2R results
May 2024Start taking orders for alkaline water electrolyzers in 2025 (the Japanese release; the English release says it plans to start commercial activity in 2025). Aims for sales of about ¥100 billion around 2030
December 2024To win a 20% share of the world's major electrolyzer markets around 2030 (the Japanese release says mainly Europe, North America and Asia; the English release names Europe, North America and India). The Japanese release also says that few projects in the world are actually operating stably
July 2025First order for a 1 MW-class containerized unit (an entry model), described as a way into larger systems
October 2025Says it moved to the full commercialization phase from fiscal 2025
What could not be confirmed

None of the following appears in the primary sources we checked Not yet confirmed.

Sales, profit and headcount for hydrogen alone; specific orders for 100 MW-plus systems; the current status and site of the Malaysian project (Green Innovation Fund Phase 2); evidence that the Finnish unit has started producing hydrogen (only the plan for around July 2026 is stated); and the individual amount of the NEDO subsidy Asahi Kasei receives. The company's releases also cite forecasts of installed electrolyzer capacity from outside bodies; those are market estimates and this article does not use them.

8. What the company is aiming for in hydrogen energy

We separate what the company says from what we read into it. Inference marks our own interpretation of primary sources.

What can be readPrimary evidenceCategory
It aims to be a leading supplier of water electrolysis, that is, of equipment and componentsThe company wrote in December 2024 and again in October 2025 that it intends to become a leading supplier in water electrolysis and a core player in the GX supply chainSourced (company target)
It splits products by use: atmospheric-pressure alkaline for large units, pressurized containerized for small and distributed onesThe September 2024 release says Aqualyzer suits mass, low-cost production with large atmospheric-pressure electrolyzers, while containerized units cost less, need less space and arrive soonerSourced
It supports chlor-alkali and water electrolysis with one production base, spreading the investment riskThe new plant can make frames and membranes for both; the company says this lets it keep and expand its earnings base while making advance investment in hydrogen (Japanese release)Sourced / Inference (the intent to spread risk)
In the near term, sales may start from small units, components and service rather than large systemsThe only disclosed order is one 1 MW-class unit, and the company says it will keep supporting maintenance and operation after delivery. No large order has been disclosedInference
It is also preparing for the next-generation AEM methodStake in Ionomr (December 2023). The Securities Report describes AEM as a next-generation membrane from which large improvements in both performance and cost are expectedSourced / Inference (the intent to prepare)
One inference in detail

Our reading that the company is spreading investment risk between chlor-alkali and water electrolysis rests on how the new plant is designed. In its December 2024 release the company admitted that it remains unclear when a hydrogen society will become a reality, yet it said the new facilities will be able to make frames and membranes for chlor-alkali as well, so that it can respond to both the uncertain expansion of the hydrogen market and growing chlor-alkali demand Sourced. That reads as a design that keeps a use for the plant even if water electrolysis demand arrives later than expected. The company does not say "to spread risk", so this is our interpretation Not yet confirmed.

9. Map of partnerships in hydrogen energy

Asahi Kasei's partnerships in hydrogen energy Only relationships stated in official releases and documents; press-reported ties are excluded Asahi Kasei Electrolysis systems JGC Holdings Joint GI Fund proposal De Nora (Italy) MOU: containerized units Gentari Hydrogen 60 MW-class MOU (status unknown) Cefmof (Finland) 1 MW-class order (July 2025) Ionomr Innovations Stake in AEM membranes (Dec 2023) NEDO and METI Commissions, grants, subsidies Joint development / MOU Supply / order Equity stake (dotted) / public funding (solid)
Fig. 2 Asahi Kasei's partnerships in hydrogen energy. Sources: Asahi Kasei releases (November and December 2023, September and December 2024, July 2025) and NEDO public documents. Only relationships stated in official materials are shown. For the Gentari project, NEDO noted in July 2025 that Phase 2 had its overseas demonstration site under review (it does not name Malaysia), and we could not confirm the current status. An MOU does not mean a contract or a project has been carried out.

10. Technologies, products and services

The company has two product lines. Both are alkaline water electrolysis, and performance figures are the manufacturer's stated values (the brochure's "expected values") that vary with operating conditions.

ProductWhat official materials sayNote
Aqualyzer (large)Built from 10 MW basic units (modules) combined for large scale. Electrolyzer, membrane, electrodes and control system supplied together. The company says its large atmospheric-pressure electrolyzers suit mass, low-cost hydrogen production10 MW-class demonstrated at FH2R, 0.8 MW modules in Kawasaki
Specifications of the 100 MW Aqualyzer system (brochure, expected values)H₂ production rate 20,000 Nm³/h; 10 modules; production ratio (operating range) 15-100%; power consumption 4.4 kWh/Nm³ (DC); H₂ pressure at stack discharge 0.5 barG; deionized water consumption 0.9 L/Nm³; H₂ purity up to 99.999% (with purification)The brochure notes the figures are "expected values" that may vary with operating conditions. Not compared with other makers' values
Aqualyzer-C³ (containerized)1 MW-class. An entry model with the equipment needed for hydrogen production housed in a container. The Finnish unit produces about 400 kg/day, enough to refill about three fuel cell vehicles per hourThe July 2025 release links to the September 2024 MOU with De Nora, which covers pressurized small units of 1 to 7.5 MW
Operation and maintenance servicesRemote monitoring from operating data, predictive maintenance and operating advice. The company says it will keep supporting maintenance and operation after deliveryApplies the data-use experience from chlor-alkali
Components (cell frames and membranes)A new Kawasaki plant (fiscal 2028) is planned to make frames and membranes for both water electrolysis and chlor-alkaliComponent supply as well as equipment sales
A materials engineer's view: what decides performance and durability in a filter-press cell

The brochure illustrates the Aqualyzer cell as anode, cathode, diaphragm, cell gasket, mattress and current collector, and lists its development focus as "optimizing diaphragms, electrodes and cell structure for water electrolysis" and "improving internal circulation and uniformity of the electrolyte" Sourced. In alkaline water electrolysis the diaphragm separates the gases while passing ions and the electrodes carry out the reactions, so these two materials, and a structure that distributes the electrolyte evenly, shape cell voltage (efficiency) and life (see our explainers on alkaline water electrolysis and on electrolyzer stacks and materials). A filter-press structure that makes diaphragms and electrodes easy to replace assumes that consumable parts are changed over a long service life, and the company says it aims to reduce downtime. The specific materials and compositions of the membranes and electrodes, and measured lifetimes, could not be confirmed from official materials Not yet confirmed.

For the next-generation AEM method, the company says the absence of precious metals gives it potential on cost. That is an expression of expectation about its investee's (Ionomr's) technology, not a demonstrated result for performance or durability.

11. The risks this company carries

RiskDetailCategory
The hydrogen market's timing is hard to readThe company itself says it remains unclear when a hydrogen society will become a reality and, in the Japanese release, that few projects in the world are actually operating stablySourced
Few orders so farThe only order we could confirm is one 1 MW-class unit. There is a wide gap to the 100 MW-plus systems and the 20% share target the company sets for around 2030Sourced / Inference (the size of the gap)
Delays and project reviewsIn July 2025 NEDO recorded that delivery of some equipment for the Namie ammonia demonstration (Phase 1) was delayed and that Phase 2 had its overseas demonstration site reviewed (it also said the schedule could be recovered). Asahi Kasei treats the Malaysian project as Phase 2Sourced (NEDO's record)
Plans keep changingFrom "bring to market by 2025" (October 2022), to "start taking orders in 2025" (May 2024), to a smaller unit being ordered first (July 2025). The new plant's investment moved from about ¥35 billion to about ¥31 billionSourced
Reliance on public supportThe Kawasaki pilot plant relies on a Green Innovation Fund subsidy and the new plant on a GX Supply Chain Development subsidy (up to one third)Sourced / Inference (the degree of reliance)
CompetitionThe 2021 business strategy vision names thyssenkrupp and Nel, among others, as competitors. The company targets a 20% share around 2030; this article does not assess whether it will be reachedSourced (the company's own listing)
Hard to verify from outsideSales, profit, headcount and R&D spending for hydrogen are not disclosed, so progress cannot be checked from the financial statementsNot yet confirmed

12. Glossary

Alkaline water electrolysis
Splitting water into hydrogen and oxygen in an alkaline electrolyte, with a diaphragm keeping the gases apart. It has a long record at large scale.
Ion-exchange-membrane chlor-alkali electrolysis
An industrial process that electrolyzes brine to make chlorine, caustic soda and hydrogen. Asahi Kasei commercialized it in 1975.
Module
A building block made of the electrolyzer itself and minimal peripheral equipment. Asahi Kasei uses a 10 MW-class unit as the base and combines several for large scale.
FH2R
Fukushima Hydrogen Energy Research Field, a NEDO-sponsored hydrogen production facility in Namie, Fukushima.
GI Fund
NEDO's Green Innovation Fund, which supports R&D and demonstration in priority fields toward carbon neutrality by 2050.
GX Supply Chain Development program
A METI program that supports building domestic manufacturing supply chains in green transformation (GX) fields.
FEED
Front-end engineering design, the design stage that follows a feasibility study.
AEM
Anion exchange membrane. A membrane that passes hydroxide ions; electrolysis using it is called AEM water electrolysis.
Nm³
A gas volume converted to standard conditions (0 °C, 1 atmosphere), used for hydrogen output.
Securities Report
The annual report that Japanese listed companies must file under the Financial Instruments and Exchange Act (yuka shoken hokokusho).
Conceptual hero image for Asahi Kasei
Fig. 3 Concept image of an alkaline water electrolyzer installation (an AI-generated concept; it does not depict an actual facility or product).

13. References

  1. Asahi Kasei 135th Securities Report, April 2025 to March 2026 (in Japanese). Sales, R&D, capital expenditure, segment results, hydrogen business, AEM membranes and the corporate venture investment framework. https://www.asahi-kasei.com/content/dam/asahi-kasei/jp/ja/ir/library/financial-report/pdf/135j-0624.pdf
  2. Asahi Kasei (Tokyo Stock Exchange disclosure) Consolidated Financial Results for the Year Ended March 2026, Japanese GAAP (12 May 2026) (in Japanese). Consolidated sales, operating profit and listing venue. https://www2.jpx.co.jp/disc/34070/081220260511523883_tse-acedjpsm-34070-20260512334070-ixbrl.htm
  3. Asahi Kasei Corporate profile (in Japanese): company name, founding, establishment, head office, paid-in capital, consolidated employees as of 31 March 2026. https://www.asahi-kasei.com/jp/company/profile/
  4. Asahi Kasei Aqualyzer official website: features, chlor-alkali track record, history and participating projects. https://ak-green-solution.com/en/
  5. Asahi Kasei Aqualyzer brochure (English): cell structure, 10 MW module, specifications of the 100 MW system (expected values) and history. https://ak-green-solution.com/assets/pdf/brochure_en.pdf
  6. Asahi Kasei Asahi Kasei starts construction of alkaline water electrolysis pilot test plant for hydrogen production (7 November 2022). https://www.asahi-kasei.com/news/2022/e221107
  7. Asahi Kasei Asahi Kasei, Gentari, and JGC signed MOU on FEED study for 60 MW class alkaline water electrolyser to produce green hydrogen in Malaysia (15 November 2023). https://www.asahi-kasei.com/news/2023/e231115
  8. Asahi Kasei Asahi Kasei invests in Canadian manufacturer of anion exchange membranes (6 December 2023). https://www.asahi-kasei.com/news/2023/e231206
  9. Asahi Kasei Asahi Kasei starts operation of multi-module hydrogen pilot plant in Kawasaki (14 May 2024). FH2R, Kawasaki and Malaysia activities and the outlook. https://www.asahi-kasei.com/news/2024/e240514
  10. Asahi Kasei Asahi Kasei enters collaboration with De Nora for development and sale of small-scale containerized electrolyzers for hydrogen production (11 September 2024). https://www.asahi-kasei.com/news/2024/e240911
  11. Asahi Kasei Asahi Kasei receives governmental support to expand manufacturing capacity for green hydrogen production equipment in Japan (18 December 2024). Initial investment of about ¥35 billion and the 20% share target. https://www.asahi-kasei.com/news/2024/e241218
  12. Asahi Kasei Asahi Kasei to supply 1 MW-class alkaline-water electrolyzer to hydrogen project in Finland (30 July 2025). https://www.asahi-kasei.com/news/2025/e250730
  13. Asahi Kasei Press release on the Finnish order (30 July 2025) (in Japanese). The first order since commercialization, the entry-model positioning and the move to the commercialization phase. https://www.asahi-kasei.com/jp/news/2025/ze250730
  14. Asahi Kasei Asahi Kasei expanding capacity to manufacture system components for clean hydrogen (23 October 2025). https://www.asahi-kasei.com/news/2025/e251023
  15. Asahi Kasei Press release on the new Kawasaki plant (23 October 2025) (in Japanese). Plant outline, investment of about ¥31 billion and the 2028 start-up plan. https://www.asahi-kasei.com/jp/news/2025/ze251023
  16. Asahi Kasei Asahi Kasei Begins Installation of Containerized Alkaline-Water Electrolyzer at Finland's First Commercial Hydrogen Refueling Station (12 March 2026). https://www.asahi-kasei.com/news/2026/e260312
  17. Asahi Kasei Tanahashi Prize recognizes the robust long-term operation of the 10MW alkaline-water electrolysis system by Asahi Kasei (19 March 2026). https://www.asahi-kasei.com/news/2026/e260319
  18. Asahi Kasei Asahi Kasei joins the Hydrogen Council (28 October 2022). https://www.asahi-kasei.com/news/2022/e221028
  19. Asahi Kasei Asahi Kasei joins the Japan Hydrogen Forum to support decarbonization in the U.S. (13 July 2023). https://www.asahi-kasei.com/news/2023/e230713
  20. NEDO FH2R, one of the world's largest renewable-energy hydrogen production facilities, completed (7 March 2020) (in Japanese). Scale of FH2R: 10 MW, 1,200 Nm³ per hour at rated output, 20 MW of solar power. https://www.nedo.go.jp/news/press/AA5_101293.html
  21. NEDO Green Innovation Fund Asahi Kasei business strategy vision, Large-scale Alkaline Water Electrolysis System Development and Green Chemical Plant Demonstration (at project start) (in Japanese). Sales plan, KPIs (consumable life, equipment cost) and the company's list of competitors. https://green-innovation.nedo.go.jp/resources/pdf/hydrogen-production-water-electrolysis-utilizing/item-001/vision-asahikasei-001.pdf
  22. NEDO Green Innovation Fund Hydrogen production through water electrolysis using power from renewables: project progress, summary as of July 2025 (in Japanese). https://green-innovation.nedo.go.jp/project/hydrogen-production-water-electrolysis-utilizing/progress/
  23. Asahi Kasei Press release on GX Supply Chain Development program selection (18 December 2024) (in Japanese). The executives' comments on the uncertain start of the hydrogen market and the 20% share target. https://www.asahi-kasei.com/jp/news/2024/ze241218_2.html
  24. Asahi Kasei Press release on the Kawasaki pilot plant (14 May 2024) (in Japanese). Details of FH2R (about 200 cells, over four years of operation) and the 2030 sales ambition. https://www.asahi-kasei.com/jp/news/2024/ze240514.html

14. Claim-to-source audit

Claim in the articleCategorySource
Legal name, head office, founding, paid-in capital, 47,895 consolidated employees (31 March 2026)SourcedReference 3 https://www.asahi-kasei.com/jp/company/profile/
Listing venue (Tokyo Stock Exchange) and consolidated net sales of ¥3,074,505 million and operating profit of ¥231,200 million (year to March 2026)SourcedReference 2 https://www2.jpx.co.jp/disc/34070/081220260511523883_tse-acedjpsm-34070-20260512334070-ixbrl.htm
R&D expenses of ¥110,537 million, capital expenditure of ¥222,324 million and the main Material-segment investments, Material segment sales of about ¥1,306.2 billionSourcedReference 1 https://www.asahi-kasei.com/content/dam/asahi-kasei/jp/ja/ir/library/financial-report/pdf/135j-0624.pdf
The hydrogen business is ranked as a strategic cultivation business and sits within Energy & InfrastructureSourcedReferences 1 and 15 https://www.asahi-kasei.com/content/dam/asahi-kasei/jp/ja/ir/library/financial-report/pdf/135j-0624.pdf https://www.asahi-kasei.com/jp/news/2025/ze251023
Chlor-alkali commercialized in 1975; membranes, electrolyzers, electrodes, operating technology and monitoring supplied togetherSourcedReferences 12, 15 and 5 https://www.asahi-kasei.com/news/2025/e250730 https://www.asahi-kasei.com/jp/news/2025/ze251023 https://ak-green-solution.com/assets/pdf/brochure_en.pdf
Hydrogen from water electrolysis in 1923, development begun in 2010, ALIGN-CCUS and TAKE-OFF participation from 2020SourcedReference 5 https://ak-green-solution.com/assets/pdf/brochure_en.pdf
A 10 MW-class unit (about 200 cells) at FH2R since March 2020, with over four years of operationSourcedReferences 24 and 9 https://www.asahi-kasei.com/jp/news/2024/ze240514.html https://www.asahi-kasei.com/news/2024/e240514
Scale of FH2R (10 MW, 1,200 Nm³ per hour at rated output, 20 MW of solar power)SourcedReference 20 https://www.nedo.go.jp/news/press/AA5_101293.html
Kawasaki pilot plant (0.8 MW x 4 modules): construction, trial run and opening ceremony datesSourcedReferences 6 and 9 https://www.asahi-kasei.com/news/2022/e221107 https://www.asahi-kasei.com/news/2024/e240514
MOU with Gentari and JGC Holdings on a 60 MW-class project (8,000 tonnes/year) and the 2027 demonstration targetSourcedReference 7 https://www.asahi-kasei.com/news/2023/e231115
NEDO's July 2025 record of delayed delivery of some equipment in Namie (Phase 1) and the review of the Phase 2 overseas site (Asahi Kasei treats the Malaysian project as Phase 2)SourcedReference 22 https://green-innovation.nedo.go.jp/project/hydrogen-production-water-electrolysis-utilizing/progress/
Current status and site of the Malaysian project (Green Innovation Fund Phase 2)Not yet confirmedNot stated in the primary sources we checked. https://green-innovation.nedo.go.jp/project/hydrogen-production-water-electrolysis-utilizing/progress/
Stake in Ionomr Innovations (AEM membranes, December 2023) and the company's description of AEMSourcedReferences 8 and 1 https://www.asahi-kasei.com/news/2023/e231206 https://www.asahi-kasei.com/content/dam/asahi-kasei/jp/ja/ir/library/financial-report/pdf/135j-0624.pdf
MOU with De Nora on containerized systems (September 2024) and the 1 to 7.5 MW pressurized small electrolyzers it coversSourcedReference 10 https://www.asahi-kasei.com/news/2024/e240911
Selection for the GX Supply Chain Development program (December 2024), the initial investment of about ¥35 billion, a subsidy of up to ¥11.4 billion, and the 20% share target around 2030SourcedReferences 11 and 23 https://www.asahi-kasei.com/news/2024/e241218 https://www.asahi-kasei.com/jp/news/2024/ze241218_2.html
Outline of the new plant (over 2 GW each, start-up planned in fiscal 2028, about ¥31 billion, up to one third subsidized) and the company's note that the figure may changeSourcedReference 15 https://www.asahi-kasei.com/jp/news/2025/ze251023
Order of a 1 MW-class unit by Cefmof (July 2025), the first order since commercialization and the move to the commercialization phaseSourcedReferences 12 and 13 https://www.asahi-kasei.com/news/2025/e250730 https://www.asahi-kasei.com/jp/news/2025/ze250730
Start of installation in Finland (March 2026), the plan to begin hydrogen production around July 2026, about 400 kg/dayNot yet confirmedReference 16 https://www.asahi-kasei.com/news/2026/e260312
Evidence that the Finnish unit has started producing hydrogenNot yet confirmedNot stated in the primary sources we checked. https://www.asahi-kasei.com/news/2026/e260312
The 2026 Tanahashi Prize and the units of the six recipients (Green Solution Project and Corporate Production Technology)SourcedReference 17 https://www.asahi-kasei.com/news/2026/e260319
Joining the Hydrogen Council (October 2022) and the Japan Hydrogen Forum (July 2023)SourcedReferences 18 and 19 https://www.asahi-kasei.com/news/2022/e221028 https://www.asahi-kasei.com/news/2023/e230713
“Bring to market by 2025” (October 2022), and “start taking orders in 2025; sales of about ¥100 billion around 2030” (May 2024)SourcedReferences 18 and 9 https://www.asahi-kasei.com/news/2022/e221028 https://www.asahi-kasei.com/news/2024/e240514
Sales plan in the 2021 business strategy vision (¥29.0 billion in fiscal 2030, ¥58.8 billion in fiscal 2035), the consumable-life KPI of four years or more, and the competitor listSourcedReference 21 https://green-innovation.nedo.go.jp/resources/pdf/hydrogen-production-water-electrolysis-utilizing/item-001/vision-asahikasei-001.pdf
Aqualyzer 100 MW system specifications (20,000 Nm³/h, 4.4 kWh/Nm³ (DC) and others, expected values), cell structure, filter-press design and servicesSourcedReference 5 https://ak-green-solution.com/assets/pdf/brochure_en.pdf
Features of the containerized unit (Aqualyzer-C³) and the split between large atmospheric-pressure and small pressurized unitsSourcedReferences 13 and 10 https://www.asahi-kasei.com/jp/news/2025/ze250730 https://www.asahi-kasei.com/news/2024/e240911
Sales, profit, headcount and R&D spending for hydrogen alone, orders for 100 MW-plus systems, and the individual NEDO subsidy amountNot yet confirmedNot stated in the primary sources we checked; this article does not estimate them. https://www.asahi-kasei.com/content/dam/asahi-kasei/jp/ja/ir/library/financial-report/pdf/135j-0624.pdf
The four-type classification of hydrogen companies (electrolyzers primary, materials & components secondary)Our calculationOur own classification. Company names are examples from this series
The new plant as a way of spreading investment riskInferenceOur own interpretation. The company says it can “respond to both” markets
Near-term sales may start from small units, components and serviceInferenceOur own interpretation, based on the only disclosed order being a 1 MW-class unit
Preparing for the next-generation AEM methodInferenceOur own interpretation of the stake in Ionomr

Last updated October 2026 / Troy Technical
Figures in this article come from Asahi Kasei's Securities Report, financial results, official releases and the Aqualyzer brochure, and from NEDO public documents. No research-firm market estimates have been used. Product performance values are the manufacturer's stated (expected) values, and values measured under different conditions or scales are not set against one another. Company plans and targets are not yet confirmed and are not things that have happened. Passages marked "Inference" are this article's interpretation of primary sources. This article is not advice on handling hydrogen.